(Victorville)– – Additional work on the LaMesa/Nisqualli Interchange Project will continue in the median over the next couple of weeks as crews will require the nighttime closure of the two inside lanes of both northbound and southbound Interstate 15 between Bear Valley Road and Palmdale Road.
Currently scheduled lane closures for both directions of I-15 will continue through Wednesday, April 25th (weather permitting). However, additional lane closures are now scheduled for Thursday, April 26th and Friday, April 27th to allow crews to safely transfer construction materials inside the protected median for ongoing bridge support efforts.
No detour is required as one lane will remain open at all times. Motorists are encouraged to slow down in construction zones and seek alternative times of travel when possible.
Please note that additional lane closures will be required in the weeks ahead, but schedules are unclear at this time because of potential weather conditions that may effect construction production rates. Additional advance notice will be provided once schedules are identified.
Location Days Hours Details
I-15 (both directions) btwn
Bear Valley and Palmdale Rd.
Thursday, April 26th
Northbound: 10:00pm – 5:00am
Southbound: 9:00pm – 4:00am
#1 and #2 Lanes (inside lanes
adjacent to median)
I-15 (both directions) btwn
Bear Valley and Palmdale Rd. Friday, April 27th
Northbound: 11:00pm – 5:00am
Southbound: 10:00pm – 4:00am
#1 and #2 Lanes (inside lanes
adjacent to median)